CANINO - ITALY

CANINO - ITALY

Project Date
10/07/2019 - 31/05/2020

Type of plant
EPC  PV Revamping

Client
Phenix Renewable srl

 

Group 50Peak Power

24,4 MWp

 

In 2019 ESI worked as EPC for the revamping of a photovoltaic power plant of 24,4 MW in the province of Viterbo, in the so- called district Sugarella.

The plant, already existing and in function for 7 years, registered serious problems both on the functioning and the sustainability. 
ESI has carried out the revamping of the PV modules, tracker and the low voltage distribution line.

The renovated power plant is characterized by an increase of the production thanks to the installation of a totally electrical mono-axial tracker, with the elimination of hydraulic oil.

Save
Cookies user prefences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Read more
Statistiche - Analytics
Google Analytics
Accept
Decline
Cookie Funzionali
Cookie di Sessione del Sito Web
Accept
Decline