SA CASETA e BINATRIA - SPAGNA

SA CASETA e BINATRIA - SPAGNA

Project Date

SA CASETA
09/03/2020 - 18/12/2020

BINATRIA
15/09/2020 - 21/04/2021

Type of plant
EPC PV PLANT

Client
ENEL GREEN POWER SPA

 

Group 50Peak Power

22 MWp   and    15 MWp

 

In 2019 UTE PV4BALEARI (a company controlled by ESI Spa), as EPC contractor, was awarded the construction of two photovoltaic plants called "Sa Caseta" and "Binatria", on the island of Palma de Mallorca, respectively of 22 MWp and 15 MWp, in favor of two Spanish companies controlled by Enel Green Power SpA

The construction of the two plants involves the design and construction of civil, electromechanical and electrical works and the installation of photovoltaic trackers, inverters and medium and low voltage connection lines.

The construction of this plant follows sustainable engineering criteria and applies Enel Green Power's 'Sustainable Construction Site' model, the installation of photovoltaic solar panels will be planned to cover part of the energy needs during the works and measures for water saving will be taken installing reservoirs and rain collection systems.

Thanks to this project, our team proves to acquire more and more skills and experience in the construction of high-power photovoltaic systems.